Legal Remedies for Home Buyers Facing Delayed Possession of Property

When home buyers invest their hard-earned money in purchasing a property, they rightfully expect timely possession of their new home. Unfortunately, there are several situations where the procedure could go disappointing. The builder may fail to deliver the property to the buyer within the stipulated time frame (or, in some cases, even after a lengthy […]

Amit Cargo Agency

Location : Naraina Industrial Area Phase-1, New Delhi Amount Paid To Builder : Rs. 52,41,473/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 75,32,948/- Background The case study revolves around Amit Cargo Agency, a cargo agency based in Naraina Industrial Area, Phase-1, New Delhi, represented by its proprietor, Mr. Chaman Lal […]

Inder Narain Gupta

Location : Anand Vihar, New Delhi Amount Paid To Builder : Rs. 1,59,581/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 4,27,313/- Background The case involved a payment dispute with the builder. The client sought a refund with interest for an amount that had been stuck for several years. Through their […]

Mamta Dewan

Location : Vivekanada Puri, Delhi Relief Sought : Delay Penalty Amount Received From Builder : Rs. 4,27,376/- Background This case study revolves around Mamta Dewan, a tile manufacturer residing in Vivekanand Puri, Delhi-110007. Maxleben Advisory took over the case to provide the right legal advice to the client. Mamta Dewan had entered into a legal […]

Dhruv Dua

Location : Kalkaji, Delhi Amount Paid To Builder : Rs. 36,53,737/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 63,94,257/- Background This case study involves Dhruv Dua, a chartered accountant residing in Kalkaji, New Delhi, as the client. The client entered an MOU with the builder in 2021. However, due to […]

Arun Dua

Location : Kalkaji, New Delhi Amount Paid To Builder : Rs. 36,53,737/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 63,89,038/- Background This case study revolves around a dispute between Arun Dua, the client, and the builder. Arun Dua seeks relief in the form of a refund with interest for the […]

Deepak Roshan

Location : Sector 41, Noida Amount Paid To Builder : Rs. 41,21,118/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 7,159,102 Background Doctor Deepak Roshan, working as a Senior Consulting Practitioner in Apollo Hospitals, Noida, found himself in a real estate dispute where he sought a refund with interest from a […]

Ritu Gupta and Peeyush Gupta

Location : Noida, Uttar Pradesh Amount Paid To Builder : Rs. 78,13,892/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 1,15,68,281/- Background Ritu Gupta and Peeyush Gupta entered into a Memorandum of Understanding (MOU) with a builder agent. However, due to unforeseen situations and dissatisfaction with the project’s progress, they decided […]

Sangeeta Malik

Location : Sector 71,Noida Amount Paid to Builder : Rs. 6,13,000/- Relief Sought : Refund With Interest Amount Received From Builder : Rs. 10,23,121/- Background In this particular case, Sangeeta Malik, a resident of Sector 71, Noida, entered into a Memorandum of Understanding (MOU) with the promoter on September 24, 2020. However, the client’s amount […]

5 Vital Components of a Builder-Buyer Dispute

Building your dream house is an exciting journey. Still, unfortunately, it can sometimes lead to disagreements and disputes between buyers and builders. Contractual difficulties, quality problems, and building delays are just a few possible causes of these disputes. Understanding your rights as a buyer and the important factors that can affect a builder-buyer dispute. In […]